Tag Archive: policy


Tamil Nadu solar policy aims to achieve 3GW by 2015

3% solar RPO requirement till December 2013
6% solar RPO requirement from 2014

RPO to be applicable to:

1. Special Economic Zones (SEZs)
2. Industries guaranteed with 24/7 power supply
3. IT Parks,Telecom Towers
4. All Colleges & Residential Schools
5. Buildings with a built up area of 20,000 sq.m. or more

This mechanism will require generation of 1000 MW by 2015.

The 3000 MW of Solar Power will be achieved through Utility Scale Projects, Rooftops and under REC mechanism as follows:

  Utility Scale (MW) Solar Roof Tops (MW) REC (MW) Total(MW)
 

(a)

 

(b)

 

(c)

(a)+(b)+ (C)
2013 750 100 150 1000
2014 550 125 325 1000
2015 200 125 675 1000
Total 1500 350 1150 3000

GBI for domestic rooftop consumers:

All domestic consumers will be encouraged to put up roof-top solar installations. A generation based incentive (GBI) of Rs 2 per unit for first two years,Re 1per unit for next two years,and Re 0.5 per unit for subsequent 2 years will be provided for all solar or solar-wind hybrid rooftops being installed before 31March,2014. A capacity addition of 50 MW is targeted under this scheme.
Consumers desirous of availing GBIs I hall necessarily install separate meters to measure rooftop generation.

Development of solar parks

Utility scale solar parks may comprise 250 MW in sizes of 1 to 5 MW, 600 MW in sizes of 5 to 10 MW and 650 MW of sizes above 10 MW. Solar Power projects will be developed through competitive/reverse bidding. Solar Parks with a capacity of about 50 MW each will be targeted in 24 districts.

Competitive bidding

Investments through Joint Ventures by State Public Sector Undertakings will also be encouraged at competitive tariffs.

Guaranteed single window clearance in 30 days

Various statutory clearances that are essential for the development and commissioning   of  Solar  Energy  Projects  will  be  handled  by  TEDA in co-ordination  with  the  concerned  departments/agencies.  Guaranteed single window clearance will be provided through TEDA in 30 days so that the plants can be commissioned in less than 12 months.

Net metering

Net metering will be allowed (at multiple voltage  levels)  to promote rooftop penetration.

Net  metering facility will  be extended to  Solar power  systems  installed in commercial establishments and individual homes connected to the electrical grid to feed excess power back   to the grid with “power credits” accruing  to the Photovoltaic energy producer.

Projects to evacuate power at suitable voltages as suggested below:

 

Solar PV System Size

 

Grid Connected

<10kWp 240V
10kWp to <15kWp 240V / 415V
15kWp to <5OKWp 415V
5OkWp to <100kWp 415V
> 100kWp 11Kv

Wheeling and banking charges

The wheeling and banking charges for wheeling of power generated from the Solar Power Projects, to the desired locations for captive use/third party sale within the State will be as per the orders of the Tamil Nadu Electricity Regulatory Commission.

Download the Tamil Nadu 2012 solar policy document at:

Tamil Nadu Solar Energy Policy document 2012

Install a solar panel on your rooftop to generate energy and sell it to the distribution company through the grid for money.

To encourage green energy, the Centre is planning a programme under which it will provide incentives, either financial or through a subsidy, to home owners installing a rooftop solar panel for own energy consumption, and who will sell the extra power to the grid during daytime.

The programme also contains a proposal in which a building owner can rent his rooftop to investors to set up a solar power plant.

The plan, which is still in a preliminary stage, says the electricity distribution companies can buy the power from households, either by paying money to the seller or giving subsidy in the seller’s electricity bill.

To introduce the system in India, which is prevalent in many European countries including Germany, there is a need to modify the current Electricity Act as well as develop locally suited technology, Union Minister of Power K C Venugopal told Deccan Herald.

Delhi to be first

The Delhi government is likely to be the first to implement the scheme as the government has started working on the issue. As per the Delhi Government’s proposed policy, residents can get solar power plants installed on their rooftops by signing a power purchase agreement with the company supplying power in their respective areas.

The cost of setting up such a plant in an area of 200 square metres will be between Rs 8 lakh and Rs 9 lakh.

According to the policy, house owners can either lease out their roofs to a developer, who will then set up the unit, or pay 30 per cent of the cost of installation.

The remaining 70 per cent will be financed through banks. The cost of generating each unit of power from the rooftop plant will be Rs 17.50 which the owner of the rooftop can sell to any of the power supplying companies.

The plants will be set up using the solar photo-voltaic technology as they can be easily mounted on rooftops, said an official in the Power Ministry.

The Centre which aims to produce 10,000 MW of solar energy in the 12th five year plan ( 2012-2017) with an investment of Rs 50,000 crore, has already set up 61 solar energy monitoring units across the country.

The government has started collecting radiation data from these monitoring centres and accordingly it will encourage setting up solar plants, he said.

While Gujarat and Rajasthan are ahead with installed capacity of 3,000 MW and 1,000 MW solar energy, the Centre wants other states to follow suit.

Power is money

* A house owner can install solar panel on the rooftop to meet his power needs

* He can then sell the extra power generated to distribution companies

* The owner can also rent out the space for setting up a solar power plant

* In return, discoms will either pay in cash or give subsidy in the seller’s electricity bill

The government of Andhra Pradesh today announced its solar policy. The policy does not specify any limit on the total capacity of solar power plants that can be put up under it. It also neither provides for a fixed feed-in tariff (like Gujarat did), nor does it make way for price discovery through a reverse bidding process (as in the case of the National Solar Mission).

However, the policy spells out the state’s stand on issues such as banking of power, wheeling and transmission charges, cross subsidy charges and open access.

In other words, a project developer may put up a project of any size in the State. He can either sell the power to the State’s electricity distribution company at the ‘average pooled purchase cost’ that is determined by the state electricity regulatory commission (which is today Rs 2 per unit), or can sell it to any other consumer directly, whether within or outside the State.

On banking of power (or, injecting power into the grid and drawing it back later), the policy says it allows 100 per cent banking. However, any energy injected into the grid will have to be drawn within that calendar year. No drawing of banked power will be allowed between February and June, and during the peak hours—6.30 pm to 10.30 pm. The developer will have to pay 2 per cent of energy as ‘banking charges’.

Further, if the energy is sold within Andhra Pradesh, the developer is incentivised with exemptions from wheeling and transmission charges and cross-subsidy charges, electricity duty and refund of VAT on inputs purchased for the project and the stamp duty on the registration of land for the project. However, for sales outside the state, wheeling and transmission charges, as determined by the state’s regulatory commission, applies.

A notable feature of the policy is that even the rooftop and off-grid plants will be eligible for the renewable energy certificates, under the ‘deemed injection’ clause.

To avail themselves of these incentives, project developers have to commission their projects by June 2014, whereupon they would get the incentives for seven years from the date of commissioning.

Industry wants details

The solar power industry finds the policy very friendly in terms of being facilitative, without casting a burden on the state government’s finances. Large cement plants, for instance, can discharge their renewable purchase obligations by becoming shareholders of solar power projects and buying the power. As such, there is likely to be considerable interest from the industry.

However, the Government has made public only the ‘abstract’ of the policy. The industry is keen on the details.

For instance, the technical and financial criteria are still awaited. The industry wants to be clear as to who is eligible to apply. (Uttar Pradesh, for example, said that only those who had done a project in India previously could apply.)

Finally, the industry would like grid-related codes and assurances of availability of the grid. How much of renewable power can the grid take? At which point will the metering happen? What is the policy relating to forecasting and scheduling?

These are some issues that need to be cleared out before people begin to put down money in solar projects in the State.

“While the policy states that one of its objectives is to “promote investments for setting up manufacturing facilities in the state”, the policy does not specify any domestic content requirement. This could make Andhra pradesh a very attractive market for the foreign PV module manufacturers who are backed by attractive financing options,” says Madhavan Nampoothiri, Founder and Director of RESolve Energy Consultants.

The Andhra Pradesh solar policy announced a few days ago has generally been hailed as a very investor-friendly policy and one that has the scope to make the State “another Gujarat.”

But nevertheless, some experts see red in the details.

Higher feed-in tariff

The policy does not provide a higher feed-in tariff, instead gives project developers a host of concessions, such as exemptions from several charge and tax credits on inputs, and encourages them to avail themselves of the tradeable renewable energy certificates.

The RECs can be traded in one of the two energy exchanges in India (IEX or PXIL) and the prescribed minimum price is Rs 9.3 a unit of electricity.

Fantastic, said the industry. For Ardeshir Contractor, Managing Director and CEO of Kiran Energy, the AP policy was a “dream come true.” The IFC and Bessemer Venture Parters-funded company had already been working on putting up a 50 MW project in the State and the policy made their deal sweeter.

But now it is dawning on many that things may not be all that simple. The policy, which relies heavily on the REC mechanism to induce developers to put up projects in the State, goes against the very principle of renewable energy certificates — that the entity will get the certificates only if it does not avail itself of other benefits.

The certificates are issued by the National Load Despatch Centre, a body of the Ministry of Power.

NLDC follows the guidelines of the Central Electricity Regulatory Commission (CERC).

CERC guidelines

The CERC guidelines clearly say that RECs will be available only to those developers who do not avail themselves of other concessions, such as lesser or exempt wheeling and banking. NLDC is allowed to follow the guidelines of the respective State Electricity Regulatory Commission, too. However, in the case of Andhra Pradesh, again the APERC’s guidelines also say (in Clause 6 (c) that those who get concessions are not eligible for RECs.

The big worry in the minds of investors is whether NLDC will refuse to issue RECs to the solar projects set up in Andhra Pradesh.

“The State solar policy is expected to create a serious conflict with APERC as well as CERC regulation on REC. The State Nodal Agency being appointed by APERC, would naturally follow the guidelines issued by the APERC. This means, solar project developers participating into REC mechanism might not be able to claim all the benefits that are proposed under the State solar policy,” says Vishal Pandya, Director, REConnect, a consultancy that helps companies secure and trade in RECs.

Highlights of the Uttar Pradesh Draft Solar Policy 2012:

  • This policy will come into effect from the date of issuance and shall remain in operation up to 31st  March 2017.
  • Target capacity of 1000 MW of    solar power will be achieved till March 2017 as follows:
Phase

Period

Total target capacity (MW)

I

2012-2013

II

2013-2014

150

III

2014-2015

300

IV

2015-2016

300

V

2016-2017

250

Total

1000

 

  • Time limit for commissioning of Solar PV projects will be within 12 months and 18 months in case of solar thermal    projects from the date of issue of concurrence from the Distribution licensee/utility.
  •  Solar power projects will be exempted  from Transmission  /Wheeling  and open access charges for third party sale and captive units.
  • ‘Uttar Pradesh Renewable Energy Development Fund’ shall be established for promoting generation of electricity through solar energy as well as other sources of renewable energy. Rupees 100 crores available to the Nodal Agency   under   budgetary   head   “Incentive   scheme   for   Solar   Power Generation” will be made part of this fund to start with.
  • No domestic content requirement.
  Developer MW    
1 Small 2 to 10 Experience of successfully commissioning grid connected Solar Power Project(s) aggregating at least  Rs.10  crore  in  the last three years. Net Worth*:

Rs 3.00 crore /MW or equivalent US$ derived from any of the last three years annual accounts.

Annual  turnover**:

Rs 5 crore /MW or equivalent US$ derived from any of the last three years annual accounts

2 Medium >10   to

25

Experience of successfully commissioning grid connected Solar Power Project(s) aggregating at least  Rs.  30  crore  in  the last three years. Net Worth*:

Rs 3.00 crore /MW or equivalent US$ derived from any of the last three years annual accounts.

Annual  turnover**:

Rs   5   crore   /MW   or equivalent US$ derived from any of the last three years annual accounts

3 Large > 25 Experience of successfully commissioning grid connected Solar Power Project(s) aggregating at least  Rs.  50  crore  in  the last three years Net Worth*:

Rs 3.00 crore /MW or equivalent US$ derived from  any  of   the  last three years annual accounts.  For  every MW   additional capacity,    beyond    25

MW, additional net worth of Rs. 2 crore would need to be demonstrated.

Annual  turnover**:

Rs   5   crore   /MW   or equivalent US$ derived from  any  of   the  last three years annual accounts

Internal       Resource

Generation#***:-

INR 2 Crore or equivalent  USD  per MW of the capacity, computed as five times the maximum internal resources generated during any of the last five years business operations.

See policy here:

Uttar_Pradesh_Solar_POWER-POLICY-DRAFT-2012

Powered by Headway Solar